These are the identified issues:
- it is possible to morph from a sub-process into a certain task type, but it is not possible to morph back to a sub-process.
- The idea is to be able to:
- Morph between task types and re-usable subprocesses
- Morph between embedded and ad-hoc subprocesses
- It also exist a blocker issue when trying to morph an embedded sub-process into a task - it appears an exception and the diagram is not successfully updated
- If you morph the subprocess with content, the content is hidden after morph, you have to reopen the process to see the content again
- clones
-
JBPM-6829 Stunner - Morphing issues for BPMN activities
- Resolved