Uploaded image for project: 'RDO Project'
  1. RDO Project
  2. RDO-84

Antelope Release Preparation

    XMLWordPrintable

Details

    • Story
    • Resolution: Done
    • Undefined
    • RDO Bobcat
    • None
    • None
    • None
    • False
    • Hide

      None

      Show
      None
    • False

    Description

      Antelope GA is close, libraries will be released soon and we need to get RDO ready for it.

      Important Dates:-

      Nov 14 - Nov 18 - Milestone 1
      Jan 02 - Jan 06 - Milestone 2
      Feb 06 - Feb 10 - Final release for non-client libraries
      Feb 13 - Feb 17 - Milestone 3 - Feature Freeze, Final release for client libraries
      Feb 27 - Mar 03 - RC1 target week
      Mar 13 - Mar 17 - Final RCs and intermediary releases
      Mar 20 - Mar 24 - Antelope release

      Issue for Zed preparation as reference - https://issues.redhat.com/browse/RDO-38
      Etherpad  - https://review.rdoproject.org/etherpad/p/antelope-release-preparation
      Process: https://www.rdoproject.org/documentation/branching/

      NOTE:- Antelope release will be based on CentOS Stream 9 ONLY

      Attachments

        Issue Links

          There are no Sub-Tasks for this issue.

          Activity

            People

              jcapitao1@redhat.com Joel Capitao
              jcapitao1@redhat.com Joel Capitao
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: