We have our proposed architecture for v2 and the 30 days demo for the data plane. We need to convert this into an implementation plan, ensuring that the scope doesn't exceed what is needed for 30 days and that the work can be shared between at least two members of the team.
Acceptance Criteria:
- Create a plan of implementation to deliver the v2 data plane architecture for the 30 days milestone
- Present the plan to the wider team so everyone has a chance to understand what's going on
- Create the necessary tasks in Jira to distribute the work
- Decide if the implementation plan is realistic for the 30 day milestone
Additional Information
- relates to
-
MGDOBR-1273 Implement integration tests for ManagedBridge custom resource
- Closed
-
MGDOBR-1275 Impelement integration tests for ManagedProcessor custom resource
- Closed
-
MGDOBR-1006 Let Shard provision Camel Processor, data plane - (Camel DSL / KNative integration)
- Closed
-
MGDOBR-1237 Split shard-operator-integration-tests for v1 and v2
- Closed