Epic
 - 
    Resolution: Done
 - 
    
Major
 - 
    0.10.1
 - 
    None
 
- 
        Phase 1: Kogito Serverless Workflow Cloud Implementation
 - 
        In Progress
 - 
        High
 - 
        0% To Do, 0% In Progress, 100% Done
 
- 
        2020 Week 22-24 (from May 25), 2020 Week 25-27 (from Jun 15), 2020 Week 28-30 (from Jul 6), 2020 Week 31-33 (from Jul 27), 2020 Week 34-36 (from Aug 17)
 
Placeholder EPIC for tasks related to the first phase of the Serverless implementation on cloud.
Design and PoC phase
- is related to
 - 
                    
KOGITO-1118 Serverless Workflow MVP
-         
 - Resolved
 
 -         
 - 
                    
KOGITO-2562 Serverless Workflow support on Operator
-         
 - Resolved
 
 -         
 - 
                    
KOGITO-2344 Support for Kubernetes Builds on Operator
-         
 - Closed
 
 -