Since May 26 (when I ran this job w/ tests disabled), VPE build takes over 4hrs to run.
We used to have 219 tests; now we have only 11 (perhaps because they take too long, they timeout and fail).
Could the long-running integration tests be split out from the short-running junits / bot tests?
http://devstudio.pad.engineering.redhat.com/4
Or is a better solution to build & publish in this job, THEN run tests as a downstream job (or downstream job config within the same job, if we don't care about multiplatform testing) ?