Uploaded image for project: 'Red Hat Advanced Cluster Management'
  1. Red Hat Advanced Cluster Management
  2. ACM-16215

Virtualization - Backup and restore Virtual Machines using Policy

XMLWordPrintable

    • False
    • None
    • False
    • Hide

      Provide the required acceptance criteria using this template.
      * ...
      Show
      Provide the required acceptance criteria using this template. * ...
    • None

      Value Statement

      Allow users to select one or more VMs running on managed clusters and create a backup schedule using an ACM  Policy.

      Allow restoring a VM's backup on a managed cluster using an ACM Policy.

      Definition of Done for Engineering Story Owner (Checklist)

      Development Complete

      • The code is complete.
      • Functionality is working.
      • Any required downstream Docker file changes are made.

      Tests Automated

      • [ ] Unit/function tests have been automated and incorporated into the
        build.
      • [ ] 100% automated unit/function test coverage for new or changed APIs.

      Secure Design

      • [ ] Security has been assessed and incorporated into your threat model.

      Multidisciplinary Teams Readiness

      • [ ] Create an informative documentation issue using the Customer

      Portal Doc template that you can access from [The Playbook](

      https://docs.google.com/document/d/1YTqpZRH54Bnn4WJ2nZmjaCoiRtqmrc2w6DdQxe_yLZ8/edit#heading=h.9fvyr2rdriby),

      and ensure doc acceptance criteria is met.

      • Call out this sentence as it's own action:
      • [ ] Link the development issue to the doc issue.

      Support Readiness

      • [ ] The must-gather script has been updated.

              vbirsan@redhat.com Valentina Birsan
              vbirsan@redhat.com Valentina Birsan
              Thuy Nguyen Thuy Nguyen
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

                Created:
                Updated:

                  Estimated:
                  Original Estimate - 2 weeks
                  2w
                  Remaining:
                  Remaining Estimate - 2 weeks
                  2w
                  Logged:
                  Time Spent - Not Specified
                  Not Specified