Uploaded image for project: 'WildFly'
  1. WildFly
  2. WFLY-576 Testsuite tasks (tracking)
  3. WFLY-609

TS: Move smoke and integration tests before the domain stuff.

    XMLWordPrintable

Details

    • Sub-task
    • Resolution: Done
    • Major
    • None
    • None
    • None
    • None

    Description

      {query}
      (21:31:55) bstansberry: OndrejZizka1: I'd like to re-order the testsuite execution a bit but am a bit lost on what's driving the current order
      (21:33:11) bstansberry: OndrejZizka1: it would be better if smoke and integration tests ran before the domain stuff, as the domain stuff is slow and just delays an overall failure if one of the more numerous smoke/integration tests fails{query}