      TEIID-3282 changed the semantics of the WEEK function to use the iso behaviour.

      The Vertica database has WEEK_ISO function that returns the iso week, but the translator does not have that alias set.

      This results in the query (the datevalue in question is 2000-12-31)

      select week(datevalue) from source.largea where intkey = 365
      

      to return 54, when the correct value is 52.