Uploaded image for project: 'OpenShift Storage'
  1. OpenShift Storage
  2. STOR-2368

[Upstream Cycle] GA - Recover from volume expansion failure

XMLWordPrintable

    • Recover from Volume Expansion
    • Future Sustainability
    • 0% To Do, 0% In Progress, 100% Done
    • False
    • Hide

      None

      Show
      None
    • False
    • Not Selected
    • None
    • 2

      Epic Goal*

      We have been driving recover from volume expansion failure, feature in upstream for awhile now. Although it is enabled by default in both upstream and downstream in v1.32, since feature is still in beta - it is at risk of removal from Kubernetes code.

      So, we need to move the feature GA in upstream.
       
      Why is this important? (mandatory)

      Moving this feature to GA in upstream is important, because all perpetually beta features are at risk of removal from Kubernetes code.

      This will also allow us to harden all aspects of volume resizing.

       
      Scenarios (mandatory) 

      Provide details for user scenarios including actions to be performed, platform specifications, and user personas.  

      1.  

       
      Dependencies (internal and external) (mandatory)

      What items must be delivered by other teams/groups to enable delivery of this epic. 

      Contributing Teams(and contacts) (mandatory) 

      Our expectation is that teams would modify the list below to fit the epic. Some epics may not need all the default groups but what is included here should accurately reflect who will be involved in delivering the epic.

      • Development - 
      • Documentation -
      • QE - 
      • PX - 
      • Others -

      Acceptance Criteria (optional)

      Feature should be GA and enabled by default in Kubernetes 1.34
        

      Drawbacks or Risk (optional)

      Reasons we should consider NOT doing this such as: limited audience for the feature, feature will be superseded by other work that is planned, resulting feature will introduce substantial administrative complexity or user confusion, etc.

      Done - Checklist (mandatory)

      The following points apply to all epics and are what the OpenShift team believes are the minimum set of criteria that epics should meet for us to consider them potentially shippable. We request that epic owners modify this list to reflect the work to be completed in order to produce something that is potentially shippable.

      • CI Testing -  Basic e2e automationTests are merged and completing successfully
      • Documentation - Content development is complete.
      • QE - Test scenarios are written and executed successfully.
      • Technical Enablement - Slides are complete (if requested by PLM)
      • Engineering Stories Merged
      • All associated work items with the Epic are closed
      • Epic status should be “Release Pending” 

              hekumar@redhat.com Hemant Kumar
              hekumar@redhat.com Hemant Kumar
              None
              None
              Chao Yang Chao Yang
              None
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated:
                Resolved:

                  Estimated:
                  Original Estimate - 2 weeks Original Estimate - 2 weeks
                  2w
                  Remaining:
                  Remaining Estimate - 0 minutes
                  0m
                  Logged:
                  Time Spent - 3 weeks