Uploaded image for project: 'Red Hat Process Automation Manager'
  1. Red Hat Process Automation Manager
  2. RHPAM-233

Append feature doesn't work properly in swimlanes

    XMLWordPrintable

Details

    • Bug
    • Resolution: Won't Do
    • Minor
    • None
    • 7.0.0.GA
    • Eclipse Tooling
    • devstudio-is-11.3.0.GA

    • User Experience
    • CR3
    • Hide
      1. Open or create new business process (jBPM process diagram)
      2. Add Swmilane to the process
      3. Put for example User Task somewhere near the boundaries of the Swimlane from previous step
      4. Right click on the User Task from the previous step
      5. Select option Append Activity -> Tasks -> User Task
      6. You will obtain something similar to the attached screenshot
      Show
      Open or create new business process (jBPM process diagram) Add Swmilane to the process Put for example User Task somewhere near the boundaries of the Swimlane from previous step Right click on the User Task from the previous step Select option Append Activity -> Tasks -> User Task You will obtain something similar to the attached screenshot

    Description

      If the Append Activity/Event/Gateway feature is used near the boundary of the swimlane, then the appended element is not visible - see the attached screenshot. Appending of the element should cause either expansion of the lane (this is case for sub-processes) or appended element should be visible without no more actions needed.

      Reproduced on:
      devstudio-is-11.3.0.GA

      Attachments

        Activity

          People

            kverlaen@redhat.com Kris Verlaenen
            rh-ee-jomarko Jozef Marko
            Jozef Marko Jozef Marko
            Jozef Marko Jozef Marko
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: