Uploaded image for project: 'Red Hat Process Automation Manager'
  1. Red Hat Process Automation Manager
  2. RHPAM-2020

Error for process diagram containing multiple instance user tasks

    XMLWordPrintable

Details

    • Bug
    • Resolution: Done
    • Major
    • 7.4.0.GA
    • 7.3.0.GA
    • Business Central
    • None
    • RHPAM 7.3 CR2 Business Central

    • 1
    • CR1
    • Hide

      Import the following project:
      https://gitlab.com/pam-issues/parallel-task
      Start the process with default inputs.
      Show the diagram of the process instance.

      Show
      Import the following project: https://gitlab.com/pam-issues/parallel-task Start the process with default inputs. Show the diagram of the process instance.
    • 2019 Week 14-16, 2019 Week 17-19

    Description

      When a process model contains a multiple instance user task, if the user open the diagram of the running instance s/he gets the following error:

      Uncaught exception: Exception caught: (SyntaxError) : Failed to execute 'querySelector' on 'Document': '#processDiagramDiv svg [bpmn2nodeid=_89C732BD-E251-4135-8BBD-B570DE79EEEC:1] ' is not a valid selector. Caused by: (SyntaxError) : Failed to execute 'querySelector' on 'Document': '#processDiagramDiv svg [bpmn2nodeid=_89C732BD-E251-4135-8BBD-B570DE79EEEC:1] ' is not a valid selector.

      Even the user task badge is not correctly computed: it displays 1 while the actual value is 3 (in my example)

      Attachments

        Activity

          People

            cnicolai@redhat.com Cristiano Nicolai
            dmarrazz@redhat.com Donato Marrazzo
            Jan Stastny Jan Stastny
            Jan Stastny Jan Stastny
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: