Rollback on checkpoint of OVS bridge left OVS system interface deactivated

Linking RHIVOS CVEs to...Migration: Automation ...SWIFT: POC ConversionSync from "Extern...XMLWordPrintable

    • No
    • Moderate
    • 2
    • rhel-net-mgmt
    • ssg_networking
    • 3
    • False
    • False
    • Hide

      None

      Show
      None
    • None
    • RHEL-9.5 Doc week/Last fixes, NMT SST - Future releases
    • Hide

      Definition of Done:

      Please mark each item below with ( / ) if completed or ( x ) if incomplete:

      ( ) The acceptance criteria defined below are met.

      Given a system administrator configures an OVS bridge and an OVS interface with the same name on a system with NM and sets up network configurations with checkpoint created for rollback purposes, 

      When they reactivate the OVS port after the OVS interface activation, 

      Then, the OVS interface profile is reactivated successfully without any problems.

       

      Definition of Done:

      • The implementation meets the acceptance criteria
      • Integration tests are written and pass
      • The fix is part of a downstream build attached to an errata
      • The fix is backported into RHEL-9.4

      ( ) Code changes are included in a downstream build attached to an errata.


      ( ) All required testing (manual and/or automated) passes successfully.


      ( ) Related documentation updates (if applicable) have been completed.

      Show
      Definition of Done: Please mark each item below with ( / ) if completed or ( x ) if incomplete: ( ) The acceptance criteria defined below are met. Given a system administrator configures an OVS bridge and an OVS interface with the same name on a system with NM and sets up network configurations with checkpoint created for rollback purposes,  When they reactivate the OVS port after the OVS interface activation,  Then, the OVS interface profile is reactivated successfully without any problems.   Definition of Done: The implementation meets the acceptance criteria Integration tests are written and pass The fix is part of a downstream build attached to an errata The fix is backported into RHEL-9.4 ( ) Code changes are included in a downstream build attached to an errata. ( ) All required testing (manual and/or automated) passes successfully. ( ) Related documentation updates (if applicable) have been completed.
    • None
    • None
    • None

      The reproduce in https://issues.redhat.com/browse/RHEL-31972 still have 10% chance of failure with a race problem when OVS port is reactivated after OVS interface activating. 

      This issue is created to track the remaining works.

        1. nm.log
          686 kB
          Gris Ge
        2. ovs_checkpoint.sh
          1 kB
          Gris Ge

              rh-ee-sfaye Stanislas Faye
              fge@redhat.com Gris Ge
              Network Management Team Network Management Team
              Vladimir Benes Vladimir Benes
              Votes:
              0 Vote for this issue
              Watchers:
              9 Start watching this issue

                Created:
                Updated:
                Resolved: