Assume this scenarios
- A
- Create a project (say, 'proj1') and upload a spreadsheet (8000rows-spreadsheet.xls)
- Login as user1 with browser1
- Login as user2 with browser2
- user1 validates the spreadsheet (8000rows-spreadsheet.xls) and user2 validates the same spreadsheet (8000rows-spreadsheet.xls)
- empty-validation-error.png reproduced
- B
- Upload another spreadsheet (8000rows-spreadsheet2.xls) to the same project 'proj1'
- Login as user1 with browser1
- Login as user2 with browser2
- user1 validates the first spreadsheet (8000rows-spreadsheet.xls) and user2 validates the second spreadsheet (8000rows-spreadsheet2.xls)
- empty-validation-error.png reproduced
- C
- Upload another spreadsheet (8000rows-spreadsheet3.xls) to another project (say, 'proj2')
- Login as user1 with browser1
- Login as user2 with browser2
- user1 validates the first spreadsheet (8000rows-spreadsheet.xls) in 'proj1' and user2 validates the third spreadsheet (8000rows-spreadsheet3.xls) in 'proj2'
- Doesn't reproduce the empty-validation-error.png
So, I guess we need to limit to only one validation per project (= GAV) at the same time. It should be limited at backend service.
- clones
-
DROOLS-2446 Concurrent spreadsheet table validation doesn't work properly
- Closed
- relates to
-
RHDM-488 Big spreadsheet decision table causes out of memory
- Closed