Uploaded image for project: 'RDO Project'
  1. RDO Project
  2. RDO-208

Caracal 2024.1 Release Preparation

XMLWordPrintable

    • Icon: Story Story
    • Resolution: Done
    • Icon: Undefined Undefined
    • RDO Caracal
    • None
    • None
    • None

      Caracal GA is close, libraries will be released soon and we need to get RDO ready for it.

      Important Dates:-

      Nov 13 - Nov 17 - Milestone 1
      Jan 08 - Jan 12 - Milestone 2
      Feb 19 - Feb 23 - Final release for non-client libraries
      Feb 26 - Mar 01 - Milestone 3 - Feature Freeze, Final release for client libraries
      Mar 11 - Mar 15 - RC1 target week
      Mar 25 - Mar 29 - Final RCs and intermediary releases
      Apr 01 - Apr 05 - Caracal release

      Etherpad  - https://review.rdoproject.org/etherpad/p/caracal-release-preparation 
      Process: https://www.rdoproject.org/documentation/branching/

      Documentation: https://www.rdoproject.org/documentation/new-release-guide/

          There are no Sub-Tasks for this issue.

              jcapitao1@redhat.com Joel Capitao
              jcapitao1@redhat.com Joel Capitao
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated:
                Resolved: