Uploaded image for project: 'OptaPlanner'
  1. OptaPlanner
  2. PLANNER-1625

[Tasks Assignment] Planning Server (solver start/feed/recovery, solutions processing and execution in jBPM runtime)

XMLWordPrintable

    • 2019 Week 41-43 (from Okt 7), 2019 Week 44-46 (from Okt 28), 2019 Week 47-49 (from Nov 18), 2019 Week 50-52 (from Dec 9), 2020 Week 01-03 (from Dec 30), 2020 Week 04-06 (from Jan 20), 2020 Week 07-09 (from Feb 10)
    • 13
    • NEW
    • NEW

      Implement the planning server startup and one-way solution processing:
      (solution "recovery" and updates not included)
      1) start solver
      2) query the available tasks
      3) apply the solutions into the jBPM server considering non disruption, etc
      4) modifying jbpm-wb queries for displaying only planned tasks that are in the "published" plann. Ej, publish only "five" tasks.

              wmedvede@redhat.com Walter Medvedeo
              wmedvede@redhat.com Walter Medvedeo
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated:
                Resolved: