Epic
-
Resolution: Obsolete
-
Major
-
None
-
None
-
Improve z-stream release process
-
False
-
False
-
To Do
-
14% To Do, 0% In Progress, 86% Done
We currently need anywhere between 5 and 10 business days to push out a z-stream release, not counting the actual code changes going into it or any QE work attached to it. This epic is about reducing the time we spend on repetitive tasks, chores or debugging avoidable issues in the build pipeline.
Goal:
- any team member can push out a z-stream release in 1 day, assuming all relevant code changes have been merged