We need to redesign our test scopes to significantly speed up our testing process.
Current State & Future Goal:
- Current: We are dealing with 3 patch versions in our current release.
- Future: We anticipate this growing to up to 5 patch versions.
- 3 versions should fall under the basic test scope.
- 2 versions should fall under the core test scope.
- Goal: Despite the increased number of versions, we must maintain a 4-day testing cycle.
Required Changes to Achieve Goal:
To meet the 4-day target, we must reduce the requirements for the basic test scope, focusing primarily on essential smoke tests.
External Constraints:
We also need to consider that the IBM testing team has limited resources during the testing phase.
Action:
We need to investigate and identify possibilities to streamline and accelerate the overall testing cycle.
Create a document with all findings and ideas on how to achieve this.
Tasks created during the investigation of this spike:
- Implement a smoke test run for test suites which takes long time https://issues.redhat.com/browse/OSSM-12423
- Support running istio integration via converter for IBM team https://issues.redhat.com/browse/OSSM-12595