Description:
Look at the movie, today is 2022/03/11, we can schedule the update time to 2022/09/11, but after click confirmation, we get the error message:
CLUSTERS-MGMT-400: Cannot set upgrade to start later than 2022-09-09T11:57:13Z
Operation ID: 8d763b30-55de-4efe-af0d-6d44c3f65859
How Reproducible:
100%
Steps to Reproduce:
1. Prepare an OSD cluster which can be upgraded.
2. Open the upgrade dialog, and at Schedule a different time, select the last time, and then click 'Confirmation'.
Actual Result:
Get the error message:
CLUSTERS-MGMT-400: Cannot set upgrade to start later than 2022-09-09T11:57:13Z
Operation ID: 8d763b30-55de-4efe-af0d-6d44c3f65859
Expected Result:
Do not provider the can-not used data in the calendar.
Additional Info: