Uploaded image for project: 'Network Edge'
  1. Network Edge
  2. NE-2051

[ExternalDNS] Migrate productization to Konflux

XMLWordPrintable

    • Icon: Epic Epic
    • Resolution: Unresolved
    • Icon: Major Major
    • None
    • None
    • None
    • [ExternalDNS] Migrate productization to Konflux
    • Quality / Stability / Reliability
    • 29% To Do, 21% In Progress, 50% Done
    • False
    • Hide

      None

      Show
      None
    • False
    • XL
    • None
    • None
    • 0

      Template:

      Networking Definition of Planned

      Epic Template descriptions and documentation

      Epic Goal

      Onboard ExternalDNSOperator to Konflux. The whole productization cycle (building, testing, releasing) should be implemented on Konflux.

      Why is this important?

      Konflux is the next-generation productization platform, and all products are expected to migrate to it as part of standardization efforts.

      Planning Done Checklist

      The following items must be completed on the Epic prior to moving the Epic from Planning to the ToDo status

      • Priority+ is set by engineering
      • Epic must be Linked to a +Parent Feature
      • Target version+ must be set
      • Assignee+ must be set
      • (Enhancement Proposal is Implementable
      • (No outstanding questions about major work breakdown
      • (Are all Stakeholders known? Have they all been notified about this item?
      • Does this epic affect SD? {}Have they been notified{+}? (View plan definition for current suggested assignee)
        1. Please use the “Discussion Needed: Service Delivery Architecture Overview” checkbox to facilitate the conversation with SD Architects. The SD architecture team monitors this checkbox which should then spur the conversation between SD and epic stakeholders. Once the conversation has occurred, uncheck the “Discussion Needed: Service Delivery Architecture Overview” checkbox and record the outcome of the discussion in the epic description here.
        2. The guidance here is that unless it is very clear that your epic doesn’t have any managed services impact, default to use the Discussion Needed checkbox to facilitate that conversation.

      Additional information on each of the above items can be found here: Networking Definition of Planned

      Acceptance Criteria

      • Every pull request merged into the openshift/external-dns and openshift/external-dns-operator repositories must trigger a build pipeline in Konflux.
      • All General Availability (GA) versions of the ExternalDNS Operator (specifically versions 1.2 and 1.3) must be onboarded to Konflux.
      • Internal documentation covering the Konflux release process and troubleshooting procedures must be created and published.
      • An advisory containing the latest base image must be shipped for the latest GA release (version 1.3).

      Dependencies (internal and external)

      N/A

      Previous Work (Optional):

      Open questions:

      Done Checklist

      • CI - CI is running, tests are automated and merged.
      • Release Enablement <link to Feature Enablement Presentation>
      • DEV - Upstream code and tests merged: <link to meaningful PR or GitHub Issue>
      • DEV - Upstream documentation merged: <link to meaningful PR or GitHub Issue>
      • DEV - Downstream build attached to advisory: <link to errata>
      • QE - Test plans in Polarion: <link or reference to Polarion>
      • QE - Automated tests merged: <link or reference to automated tests>
      • DOC - Downstream documentation merged: <link to meaningful PR>

              alebedev@redhat.com Andrey Lebedev
              alebedev@redhat.com Andrey Lebedev
              Ali Syed, Grzegorz Piotrowski
              Melvin Joseph Melvin Joseph
              None
              Votes:
              0 Vote for this issue
              Watchers:
              6 Start watching this issue

                Created:
                Updated: