XMLWordPrintable

Details

    • [4.13] Stretch Cluster
    • False
    • False
    • Green
    • NEW
    • Done
    • OCPSTRAT-146 - HA Stretch Cluster for IBM Power and IBM zSystems
    • ppc64le, s390x
    • OCPSTRAT-146HA Stretch Cluster for IBM Power and IBM zSystems
    • NEW
    • 100
    • 100% 100%

    Description

      Epic Goal

      • Verification for Stretch Cluster with OCP to understand the max 

      Why is this important?

      • Customers want to setup their OCP cluster setup in a way that they spread their 

      Scenarios
      1. setup a cluster on 3 Datacenter and adjust to the max latency the cluster runs stable

      Acceptance Criteria

      • (Enter a list of Acceptance Criteria unique to the Epic)

      Dependencies (internal and external)
      1. none

      Previous Work (Optional):
      1. 

      Open questions::
      1.

      Done Checklist

      • CI - For new features (non-enablement), existing Multi-Arch CI jobs are not broken by the Epic
      • Release Enablement: <link to Feature Enablement Presentation>
      • DEV - Upstream code and tests merged: <link to meaningful PR orf GitHub Issue>
      • DEV - Upstream documentation merged: <link to meaningful PR or GitHub Issue>
      • DEV - If the Epic is adding a new stream, downstream build attached to advisory: <link to errata>
      • QE - Test plans in Test Plan tracking software (e.g. Polarion, RQM, etc.): <link or reference to the Test Plan>
      • QE - Automated tests merged: <link or reference to automated tests>
      • QE - QE to verify documentation when testing
      • DOC - Downstream documentation merged: <link to meaningful PR>
      • All the stories, tasks, sub-tasks and bugs that belong to this epic need to have been completed and indicated by a status of 'Done'.

      Attachments

        Issue Links

          1.
          Docs Tracker Sub-task Closed Undefined Unassigned
          2.
          PX Tracker Sub-task Closed Undefined Unassigned
          3.
          QE Tracker Sub-task Closed Undefined Unassigned
          4.
          TE Tracker Sub-task Closed Undefined Unassigned

          Activity

            People

              midavies@redhat.com Michael Davies
              holgwolf Holger Wolf
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: