etcd has a 1.5 MiB limit on requests - but if it grows by the number of VMs that we have in the plan we could well exceed that limit as it's not so high
that said, plans are designed for a single target namespace and it's not clear whether migrating so many VMs to a single namespace would be a common practice in the field
So we need to include somewhere in the documentation that:
The size of the Plan should be no more than 500 VMs or Disks
etcd has a 1.5 MiB limit on requests - but if it grows by the number of VMs that we have in the plan we could well exceed that limit as it's not so high
that said, plans are designed for a single target namespace and it's not clear whether migrating so many VMs to a single namespace would be a common practice in the field
So we need to include somewhere in the documentation that:
The size of the Plan should be no more than 500 VMs or Disks
Sprint 13-MMSDOCS 2024, Sprint 14-MMSDOCS 2024
is duplicated by
MTV-1203Forklift controller error ""etcdserver: request is too large"
Closed
relates to
MTV-1203Forklift controller error ""etcdserver: request is too large"