Task
-
Resolution: Done
-
Blocker
-
None
-
None
Issue Description:
We have our proposed architecture for v2 and the 30 days demo for the control plane. We need to convert this into an implementation plan, ensuring that the scope doesn't exceed what is needed for 30 days and that the work can be shared between at least two members of the team.
Acceptance Criteria:
- Create a plan of implementation to deliver the v2 control plane architecture for the 30 days milestone
- Present the plan to the wider team so everyone has a chance to understand what's going on
- Create the necessary tasks in Jira to distribute the work
- Decide if the implementation plan is realistic for the 30 day milestone
- is related to
-
MGDOBR-1106 API versioning: Manager services and models
- Closed
-
MGDOBR-1204 Manager: Split (API) versioned artifacts into sub-modules
- Closed
-
MGDOBR-1236 Split manager-integration-tests for v1 and v2
- Closed
- relates to
-
MGDOBR-1186 API Contract between Control Plane and Data Plane
- Closed
-
MGDOBR-1187 Camel DSL Processor API - 30 days spec
- Closed
-
MGDOBR-1211 Add V2 API in the manager
- Closed
-
MGDOBR-1239 Implement processor API v2 integration tests
- Closed
-
MGDOBR-1238 Implement bridge API v2 integration tests
- Closed