Bug
-
Resolution: Done
-
Major
-
jBPM 6.5.0.Final
-
None
-
NEW
-
NEW
-
Please take a look at the attached screenshots. The simulation data for all human tasks are:
Distribution Type: Uniform Processing time (max): 8 Processing time (min): 8 Staff availability: 2 Working hours: 8
The expectation is that the first task has no wait time, if the simulation is started with 8 hours interval. This is true for a process where the tasks are handled in sequence, and even for a process with one level fork/join, but not for the attached process with two levels.
- causes
-
RHBPMS-4540 Incorrect simulation results for processes containing nested forks
- Verified