In some cases, the result of invoking an operation can be confused with the
result of the actual operation.
For example:
For a datasource resource, you can invoke the "Test Connection" operation. Once
the operation has been submitted, the "Operation History" will indicate
"Successful". This "Successful" message can easily be interrupted as the
connection to the datasource was successful when in reality, the actual test of
the datasource connection returned failed.
This is confusing to operational admins looking at this UI to test a
connection. In fact, this would mislead them to look at the wrong section and
proceed thinking the connection has been obtained when it's not, and could
possibly cause serious production ramifications. The UI should be re-worked and
be more intuitive and clear.