      1. Set up a remote EAP 6.3 server with management profile
      2. Start the remote server, enter the credentials when prompted
      3. Try to deploy a project that takes more than a few seconds (e.g. you can deploy a seam project containing the seam lib)
      4. Watch for the progress message in the status bar at the bottom of Eclipse - it will keep showing 0 %

      Show
      1. Set up a remote EAP 6.3 server with management profile 2. Start the remote server, enter the credentials when prompted 3. Try to deploy a project that takes more than a few seconds (e.g. you can deploy a seam project containing the seam lib) 4. Watch for the progress message in the status bar at the bottom of Eclipse - it will keep showing 0 %

      When I publish a very big project to a remote server and it's taking minutes, the status bar still keeps saying 0 % is complete.
      I got this issue with a remote EAP 6.3 with management profile. Not sure about file operations profile.