Uploaded image for project: 'Tools (JBoss Tools)'
  1. Tools (JBoss Tools)
  2. JBIDE-1276

Finish button enabled too soon for Seam wizard

XMLWordPrintable

    • Icon: Bug Bug
    • Resolution: Done
    • Icon: Major Major
    • 2.0.0.CR1
    • 2.0.0.Beta4
    • seam2
    • None

      EXECUTE: Start on clean workspace
      EXECUTE: Fill in first page of Create Seam Web Project
      EXECUTE: Select Seam 1.2 or Seam 2 preset
      ASSERT: Finish button should not be enabled since there are no connection nor seam runtimes defined

      Seam 1.2 currently enables finish button and result in NPE because no connection.
      Seam 2 doesn't enable finish button for some reason - should be the same logic?!

              nivologd@gmail.com Denis Golovin (Inactive)
              manderse@redhat.com Max Andersen
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated:
                Resolved: