Task
-
Resolution: Unresolved
-
Major
-
None
-
None
-
None
-
NEW
-
NEW
For now, we're looking for a one time test. Later I presume the exe model will be come the default, so these tests would just run?
To run the optaplanner turtle tests, run all tests in optaplanner-examples with the VM parameter `-DrunTurtleTests=true`. They take 48 hours to run. You can also just run one, for example NurseRosteringSolveAllTurtleTest, but don't forget that VM parameter.
Mario Fusco says you can do this to turn on the executable model:
kieBuilder.buildAll( ExecutableModelProject.class );
I presume you 'd need to hack that in `ScoreDirectorFactoryConfig.buildDroolsScoreDirectorFactory()`.
Note: I have no idea if this even make sense: those turtle tests use a drl file input and don't use the kie-maven-plugin. We're looking for a switch to just turn it on and see if they are all still green. Mario thinks it's possible, if I understand it correctly.
- is related to
-
DROOLS-2367 Executable model - Drools context (kcontext) doesn't work when used together with a global
- Closed