Planned Outage - Datacenter Move outage - 2025-06-30 01:00 UTC

XMLWordPrintable

    • 10
    • False
    • Hide

      None

      Show
      None
    • False
    • None
    • Testable

      https://pagure.io/fedora-infrastructure/issue/12603

      Planned Outage - Datacenter Move outage - 2025-06-30 01:00 UTC

      There will be an outage starting at 2025-06-30 01:00UTC,
      which will last approximately 48 hours.

      To convert UTC to your local time, take a look at
      http://fedoraproject.org/wiki/Infrastructure/UTCHowto
      or run:

      date -d '2025-06-30 01:00UTC'

      Reason for outage:

      We will be moving services and applications from our IAD2 datacenter to a new RDU3 one.

      End user services such as: docs, mirrorlists, dns, pagure.io, torrent, fedorapeople, fedoraproject.org website, and tier0 download server will be unaffected and should continue to work normally through the outage window.

      Other services may be up and down during the outage window as they are migrated over to the new datacenter.
      Contributors are advised to wait until after the outage window to resume work and report issues with services.

      Affected Services:

      All contributor facing services will be affected during the outage window. On monday non build services will be moved, and on tuesday build services will be moved.

      Ticket Link:

      https://pagure.io/fedora-infrastructure/issue/12603

      Please join #admin:fedoraproject.org / #noc:fedoraproject.org on matrix.
      Please add comments to the ticket for this outage above.

      Updated status for this outage will be available at
      https://www.fedorastatus.org/