      Directly upgrade CNV from any given z-release to any later z-release along y release is possible

      Show
      Directly upgrade CNV from any given z-release to any later z-release along y release is possible
    • Green
    • In Progress
    • VIRTSTRAT-504 - Faster upgrades
    • VIRTSTRAT-504Faster upgrades
    • 19% To Do, 0% In Progress, 81% Done
    • dev-ready, po-ready, qe-ready, ux-ready
    • Hide

      2025-10-07:
      on track, enabled also on 4.16 and 4.17.

      v4.18 and v4.19 will be enabled tomorrow....

      Show
      2025-10-07: on track, enabled also on 4.16 and 4.17. v4.18 and v4.19 will be enabled tomorrow....

      Goal

      Enable OCP-style upgrades along a z-stream for CNV. 

      The main consideration here is testing - so far CNV was thoroughly testing each upgrade which is not scaling if we'd like to enable 'free' upgrades along a z-stream. During grooming it should be assessed if this can be eased a bit.

       

      This should be initially enabled and verified for 4.17 line, as it a recent version that already has some z releases.

      Need to first apply this to staging index.

      User Stories

      • As a Cluster Admin I want to directly upgrade CNV from any given z-release to any later z-release along y release.
      • another user story

      Non-Requirements

      • Allowing any 4.Y.z to 4.Y+1.z; it's completely fine to require a single update to the latest 4.Y.z before updating to latest 4.Y+y.z and this aligns well with our guidance that you should apply the latest z-stream update before applying a y-stream update

      Notes

      • Any additional details or decisions made/needed

          1.
          upstream roadmap issue Sub-task Closed Normal Unassigned
          2.
          upstream design Sub-task Closed Normal Unassigned
          3.
          upstream documentation Sub-task Closed Normal Unassigned
          4.
          upgrade consideration Sub-task Closed Normal Unassigned
          5.
          CEE/PX summary presentation Sub-task Closed Normal Unassigned
          6.
          test plans in polarion Sub-task Closed Normal Unassigned
          7.
          automated tests Sub-task Closed Normal Unassigned
          8.
          downstream documentation merged Sub-task Closed Normal Unassigned

              kmajcher@redhat.com Krzysztof Majcher
              rhn-support-sdodson Scott Dodson
              Harel Meir Harel Meir