Objective:
- This test plan aims to ensure that the upgrade from RHEL 8.6-based CNV (and OCP) to RHEL 9.0-based CNV (and OCP) can be carried out with minimal disruption to the control plane and workloads.
- The plan also addresses live migrations from the previous version to the new RHEL 9.0-based CNV, and how machine types will be handled.
- Full T2 regression tests on both supported CNI (SDN/OVN)
Possible scenarios:
- Live Migration from RHEL 8.6-based CNV to RHEL 9.0-based CNV.
- Upgrade CNV to RHEL 9.0 without significantly disrupting the control plane and workloads.
- Tier 0 and Tier 1 testing of RHEL 9.0-based CNV.
- clones
-
CNV-24851 Validate VM latency checkup with RHEL 9 on 4.13
-