As a CNV Program Manager I want to capture the work related to managing a Z Stream Release (opening, closing) so that I can track its progress during planning and execution.
Release Opening
Jira
- Create a release version in the CNV Project
Bugzilla
- Create release version
- Create target release version
- Modify CNV Group Rules to Ensure cnv-* flag is set for this release (1.* | 2.* | 4.*)
Smartsheet
- Update release schedule with z-stream data
Product Pages
- Sync with Smartsheet release schedule data
Release Closing
GA - 1 wks
- () Set release date in the corresponding advisories in the Errata Tool
As soon after GA as possible:
Comet
- () Sync on container data with build team (Ben Oukanov) for population of Honeybadger to populate Pyxis.
Jira
- () Ensure all bugs are closed
- () Release version
CNV PgM Resources doc
- () Update Consolidated Z Stream Release Info
- () Check Releases Summary Header