GOAL
As a program manager I need to capture and track tasks that need to be completed by the program team prior to release.
PgM Tasks
Before GA
- GA-8W:
- () Update and submit EARF Form
At GA
Product Pages
- () Move this release to maintenance on the Engineering Product Pages.
- () Move the appropriate release to unsupported.
- () Create one last status with the summary "4.11.z is now unsupported".
Comet
- () Sync on container data with build team (Ben Oukanov) for population of Honeybadger to populate Pyxis.
Jira
- () Check that all Jira items have been closed: open epics, bugs, etc..., and then Release version
CNV PgM Resources doc
- () Update tab Consolidated Feature Release Info
- () Update tab Releases Summary Header
- () Update Overall Release Status section in the CNV Program Meeting Template doc