Uploaded image for project: 'Red Hat Advanced Cluster Management'
  1. Red Hat Advanced Cluster Management
  2. ACM-4026

As an admin, I can use global grafana to show the global policy view for my hubs

XMLWordPrintable

    • 5
    • False
    • None
    • False
    • Hide

      Provide the required acceptance criteria using this template.
      * ...
      Show
      Provide the required acceptance criteria using this template. * ...
    • ACM-627 - Scalability of Hub for Edge Use Cases
    • Observability Sprint 2023-09
    • No

      Value Statement

      Deliver a policy overview for the customers(Citi) to make good use of their current 5 hubs and 600+ mc.

      Scenarios

      • Show status of 10k * 10 = 100K policies. This is a global view
        1. there is a policy centric view
        2. there is also a cluster centric view

      Definition of Done for Engineering Story Owner (Checklist)

      • Deliver a grafana dashboard for the global policy overview
      • Add tests to cover the new code
      • Deliver a document for this feature

      Development Complete

      • The code is complete.
      • Functionality is working.
      • Any required downstream Docker file changes are made.

      Tests Automated

      • [x] Unit/function tests have been automated and incorporated into the
        build.
      • [n/a] 100% automated unit/function test coverage for new or changed APIs.

      Secure Design

      • [n/a] Security has been assessed and incorporated into your threat model.

      Multidisciplinary Teams Readiness

      Support Readiness

      • [n/a] The must-gather script has been updated.

       

              dbennett@redhat.com Disaiah Bennett
              clyang82 Chunlin Yang
              Hui Chen Hui Chen
              Votes:
              0 Vote for this issue
              Watchers:
              6 Start watching this issue

                Created:
                Updated:
                Resolved:

                  Estimated:
                  Original Estimate - 2 weeks, 2 days, 4 hours
                  2w 2d 4h
                  Remaining:
                  Remaining Estimate - 2 weeks, 2 days, 4 hours
                  2w 2d 4h
                  Logged:
                  Time Spent - Not Specified
                  Not Specified