T Key P Status Assignee Summary Created Updated Fix Version/s Fixed In Version Git Pull Request
Sub-task ENTSBT-125 Major Closed Chris Laprun

ENTSBT-106 Day -1: [Eng] Check EARF if it needs to be updated

 
Sub-task ENTSBT-124 Major Closed Chris Laprun

ENTSBT-106 Day -1: [Eng] CR Ready for QE [June 27]

2.1.6.CR1
Sub-task ENTSBT-123 Major Resolved Libor Fuka

ENTSBT-106 Day 0: [QE] sign-off published

 
Sub-task ENTSBT-122 Major Closed Jiri Pallich

ENTSBT-106 Day +1: [PgM] RCM tickets filed (for Java runtimes)

 
Sub-task ENTSBT-121 Major Resolved Martin Ocenas

ENTSBT-106 Day +2: [QE] Errata pushed to REL_PREP

 
Sub-task ENTSBT-120 Major Closed Naina Singh

ENTSBT-106 Day +3: [PM] Update PM asks sheet for containers

 
Sub-task ENTSBT-119 Major Closed Chetak Marulasiddappa

ENTSBT-106 Day +4: [RCM] Bits publicly available (Internal GA)

 
Sub-task ENTSBT-118 Major Closed Tomas 'Sheldon' Radej

ENTSBT-106 Day +5: [Docs] Docs Freeze + Sync to Stage + Upstream release

 
Sub-task ENTSBT-117 Major Closed Chris Laprun

ENTSBT-106 Day +5: [Eng] Pull Requests to the Catalog for the -redhat Examples

  https://github.com/fabric8-launcher/launcher-booster-catalog/pull/363
Sub-task ENTSBT-116 Major Resolved Martin Ocenas

ENTSBT-106 Day +5: [QE] Bits Availability Verification

 
Sub-task ENTSBT-115 Major Closed Naina Singh

ENTSBT-106 Day +6: [QE->PM] Supported configurations and Component details ready

 
Sub-task ENTSBT-114 Major Closed Libor Fuka

ENTSBT-106 Day +6: [QE] Documentation Final Verification (w/o RN)

 
Sub-task ENTSBT-113 Major Closed Chris Laprun

ENTSBT-106 Day +7: [Launcher] Examples Catalog Release

  https://github.com/fabric8-launcher/launcher-booster-catalog/pull/358
Sub-task ENTSBT-112 Major Resolved Stefan Sitani (Inactive)

ENTSBT-106 Day +7: [Docs] Release Notes Freeze + Sync to Stage

 
Sub-task ENTSBT-111 Major Closed Libor Fuka

ENTSBT-106 Day +8: [QE] Release Notes Final Verification

 
Sub-task ENTSBT-110 Major Closed Tomas 'Sheldon' Radej

ENTSBT-106 Day +9: [Docs] Push the Documentation and Release Notes

 
Sub-task ENTSBT-109 Major Closed James Falkner

ENTSBT-106 Day +10: [PMM] learn.openshift.com updated

 
Sub-task ENTSBT-108 Major Closed Libor Fuka

ENTSBT-106 Day +10: [QE] developers.redhat.com/launch final verification

 
Sub-task ENTSBT-107 Major Closed James Falkner

ENTSBT-106 Day +11: [PMM] Release announcement (Marketing GA)

 