[GSS](7.2.1) Not able to set as reusable sub-process process from different project

    XMLWordPrintable

Details

    • Bug
    • Resolution: Done
    • Major
    • 7.2.1.GA
    • 7.0.0.GA
    • jBPM Designer
    • None
    • ER2
    • CR1
    • ?
    • Hide
      1. Create project first
      2. create Start->End processA in project first
      3. create project second
      4. create processB in project second
      5. in processB add reusable sub-process and try to set Called Element property to processA

      Actual Result:
      You won't see processA in process suggestion list

      Expected Result:
      You will see processA in process suggestion list and will be able to set it as Callable Element

      Show
      Create project first create Start->End processA in project first create project second create processB in project second in processB add reusable sub-process and try to set Called Element property to processA Actual Result: You won't see processA in process suggestion list Expected Result: You will see processA in process suggestion list and will be able to set it as Callable Element
    • 2019 Week 02-04, 2018 Week 51-01

    Description

      It was possible before to add as reusable sub-process process from different project, but it is not valid anymore. I guess it was caused by redesign of library perspective.

      Attachments

        Issue Links

          Activity

            People

              rhn-support-tsurdilo Tihomir Surdilovic (Inactive)
              rhn-support-mputz Martin Weiler (Inactive)
              Kirill Gaevskii Kirill Gaevskii
              Kirill Gaevskii Kirill Gaevskii
              Votes:
              0 Vote for this issue
              Watchers:
              5 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: