Business Calender does not work as expected when the timer is set in some conditions

XMLWordPrintable

    • Icon: Bug Bug
    • Resolution: Done
    • Icon: Major Major
    • 7.1.1.GA
    • 7.0.1.GA
    • None
    • RHPAM 7.0.1

    • CR1
    • +
    • Hide

      Please run attached reproducer by mvn clean test.

      Show
      Please run attached reproducer by mvn clean test.
    • 2018 Week 42-44

      When using Business Calendar, timer is not set as expected if current time is :

      • before working hours ( < START_HOUR)
      • after working hours ( > END_HOUR)
      • during working hours on Holiday
      • during working hours on Weekend