POK Lab YZ Migration
-
False
-
None
-
False
-
Not Selected
-
NEW
-
To Do
-
ppc64le
-
NEW
-
M
Epic Goal
- The goal of this epic is to migrate our Power hardware out of the yellow zone network without disrupting CI.
Why is this important?
- We've been asked to vacate the YZ.
Scenarios
1. CI jobs for Power still work.
Acceptance Criteria
- Lab hardware is no longer in the YZ.
- CI jobs are still working.
- Compliance requirements are met with InfoSec.
Dependencies (internal and external)
1. Test Platform
Previous Work (Optional):
1. See yellow zone libvirt tunnel.
Open questions::
1. What additional security steps need to be taken in order to remain compliant with InfoSec standards?
Done Checklist
- CI - New set up is ACKed by InfoSec.
- Lab - Hardware is renetworked
- CI - Existing jobs are working in the new network zone.
- All the stories, tasks, sub-tasks and bugs that belong to this epic need to have been completed and indicated by a status of 'Done'.
- is related to
-
MULTIARCH-4979 Multi-Arch Z-CI Network Changes
- New