      Overview

      The milestone 7 is 2 sprints (sprint 222,223) long, ending on August 30, 2022. This epic covers the user flows to be accomplished in the UI as part of the milestone demo.

      Demo script

      NOT FINALIZED

      1. The user is able to update one of the mutable configurations for the application in the Development environment and see the existing application get automatically redeployed with the new settings.
      2. The user is able to manually promote the app and all of its components (which the user previously created by specifying a git repo and/or images and/or samples) running in the Development environment to the new environment.
      3. The user is able to switch the Development (POC) environment from “Automated” deployment to “Manual”. After that, any updates that would normally trigger a new deployment are ignored by the system.
      4. The user is able to toggle to the Topology view of the Development environment and see the deployed components and their status. This is the first iteration of topology being delivered.
      5. NEED TO finalized UX & bug fixes & determine how to pull into the UI

      Acceptance Criteria

       

      Related Documents

       

        1.
        DOD: Training materials supplied to Support/SRE Sub-task To Do Undefined Unassigned
        2.
        DOD: Training materials supplied to Support/SRE Sub-task To Do Major Unassigned
        3.
        DOD: Docs verified by QE Sub-task To Do Major Unassigned
        4.
        DOD: Docs verified by QE Sub-task To Do Undefined Unassigned
        5.
        DOD: Docs completed and merged Sub-task To Do Major Unassigned
        6.
        DOD: Docs completed and merged Sub-task To Do Undefined Unassigned
        7.
        DOD: All known issues captured and blockers resolved Sub-task To Do Major Unassigned
        8.
        DOD: All known issues captured and blockers resolved Sub-task To Do Undefined Unassigned
        9.
        DOD: All work items belonging to this Epic are complete Sub-task Closed Major Unassigned
        10.
        DOD: All work items belonging to this Epic are complete Sub-task Closed Undefined Unassigned
        11.
        DOD: Code merged for regular build/release testing in the HAC Common CI/CD framework Sub-task To Do Major Unassigned
        12.
        DOD: Code merged for regular build/release testing in the HAC Common CI/CD framework Sub-task To Do Undefined Unassigned
        13.
        DOD: CI runs successfully with test automation Sub-task To Do Major Unassigned
        14.
        DOD: CI runs successfully with test automation Sub-task To Do Undefined Unassigned
        15.
        DOD: Automated/Integrated tests complete Sub-task To Do Major Unassigned
        16.
        DOD: Automated/Integrated tests complete Sub-task To Do Undefined Unassigned
        17.
        DOD: Architectural artifacts completed, reviewed and stored Sub-task To Do Major Unassigned
        18.
        DOD: Architectural artifacts completed, reviewed and stored Sub-task To Do Undefined Unassigned
        19.
        DOD: Product Manager and UX signed off on solution Sub-task To Do Major Unassigned
        20.
        DOD: Product Manager and UX signed off on solution Sub-task To Do Undefined Unassigned
        21.
        DOD: Acceptance criteria related to this Epic has been identified and met Sub-task To Do Major Unassigned
        22.
        DOD: Acceptance criteria related to this Epic has been identified and met Sub-task To Do Undefined Unassigned

            rorai Rohit Rai
            sdoyle@redhat.com Serena Nichols
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

              Created:
              Updated:
              Resolved: