Prepared hardware that will move to RDU3 (dc-move)

    • 5
    • rhel-cle-pnp

      1. CentOS Infra issue/request

      Please file this generic issue template or feel free to select another one in the list above (Description / Choose a template)

        1. Issue Type
      • [] Issue - problem with something that was working
      • [] Feature Request - something you'd like us to add/modify/change
      • [x] Task - mostly used by CentOS Infra team for day-to-day operations or bigger plans
        1. Description

      Some machines in RDU2 will have to be prepared before they'll be powered off, and shipped to RDU3, to then be racked into existing RDU3 racks (and so then be reinstalled and added back to the existing pool)

      Items to prepare:

      • clean machines (clean reinstall or delete VMs, etc, to be analyzed on a case-by-case )
      • eventually (optional) upgrade underlying firmware for components (perfect time to do that)
      • switch mgmt ip (idrac, or else) to new ip range from RDU3
      • power machines off